HOME - GENERAL MANAGER'S REPORT

Major Capital Investments

NWSC, in various stages, has completed the following past projects.

  Projects

Donor's Fund
(HMGN and NWSC)

Total
(in million)
Donors
1.

First Water Supply& Sewerage Project

US$   11.80 US $ 3.00  US $ 14.80 WB
2. Third Water Supply & Sewerage Project US$     8.00 US $  2.50 US $  10.50 WB
3. Third Water Supply & Sewerage Project US$   27.00 US $ 4.00 US $ 32.00 WB
4. Urban Water Supply Sanitation & Rehabilitation Project US $ 15.00 US $ 4.00 US $ 19.00 WB
5. Kathmandu Valley Water Supply Improvement Project US $    15.4 US $  1.28 US $ 16.32 JICA

However, if funds are made available on time, detail survey and design shall be done to bring additional quantities of water to Network System form other major/minor new sources like Khwanglang (Tubewell) (south of valley) and Balkhu (west valley). Also minor up-grading works and service extensions are currently underway in various existing water intakes, treatment plants and storage or also in pipeline.
 

 